About yesterday



The jcb operator worked 7:30am -4:30 pm with a 1-hour lunch break and it seems that the pile just got bigger. 
This is nice rich soil which will be used for filling back the soil excavations in the food forest area, the plan being to use the extracted soil to make CSEB - Compressed Stabilized Soil Bricks = raw mud blocks with a bit of, in our case, cement (5%) 

Comments

Popular posts from this blog

A shortened week 6 : Independance Day, death and burials

On the 6th week we trained our workers on the CSEB production : how to mix, how to use the press safely, and accept or reject the blocks that are made, how to handle the blocks... and how to monitor the production. Our main person on site - not the construction foreman, but our "site clerk" and "HR director" C. is also responsible for keeping track of what's going on with the production, and sending me the daily figures so I can monitor that from my computer. We were hoping to get the JCB to dig for more soil (we asked for tenders from contractors for manual excavations and we got crazy expensive propositions), and start digging the foundations when they'd be marked, but unfortunately deaths happened in the families of the JCB operator, the foreman and the structural and building engineer, thus taking them away from work for a couple of days. Friday 6th was also a national holiday, being the commemoration of Malawi's Independanc...

Week 5 : The launch of CSEB making

So, yeah, this week saw the start of the production of our CSEB - Compressed Stabilized Earth Blocks, also called "SSB" for Stabilized Soil bricks, or BTC in French, for Blocs de Terre Comprimée (manque un S pour stabilisée mais bref).  They are much more eco-friendly than the fired bricks (using a looot of wood to get cooked) or concrete (using a loooot of (imported) cement), as these blocks should count only 5% of cement for the stabilization, and don't need any plaster or paint or any other layer on them at the end to be confortable and beautiful. So some soil has already been extracted and sieved, and kinda analyzed ( a bit too roughly unfortunately), we had a bag of cement ready, some water nearby, a large area for the curing was prepared, the machine was assembled and we were ready to start testing ! We made our first blocks on Monday afternoon, guiding the guys for the dry mixing, the wet mixing, the steps for the compression, the handling on the block...

Construction : week 2

Program this week : the JCB machine and operator will be on site from this morning 7:30, gotta be there to give instructions as the operations boss is away. Moving heaps of soil, rocks, levelling and flattening, digging some places. Then the proper structures marking and foundations digging can start ! Excitement level : \o/