Under the rain for week 8

The buildings and remaining boundary wall have been placed and marked, but now the rain is preventing the guys from digging... That should be the very last bad weather week, but when it's bad, it's really dull and impossible to work ! So the site is closed today. The tent has been put down to prevent further tearing, as the wind is really strong... and everybody sent home. That gives us time to work on the designs !


last week's markings


buuuh rain

R. the engineer could work on the foundations of the family cottages, good news, he's downsizing them, and designing them in stone now instead of the previously thought concrete ground beam. After our adjustment work session yesterday, he should have the plans ready very soon, and with that the list and quantity of necessary materials.

So now that this part is sorted, or almost, I'm working on the water sewage system design. 
And calling for volunteers among the Polytech students which are going to be on holidays for a month from Friday - maybe some of them would be interested in a free hands-on training in eco-construction ?
We could do with a bit of helping hands with all this.

Comments

Popular posts from this blog

Starting Week 4

So last week saw another change of plans on site : Tuesday was the last day of the JCB on site, where it only worked for a couple of hours before having to be brought somewhere else, requested by the preparation of the presidential elections... We're getting ready to start making CSEB anyways, I had a closer look to the soil that is being prepared and sent several emails to ask for some advice. We're going to have to go though a test phase anyways, as we're not really sure of the soil we have... it's a good one no doubt, but is it really more sandy / more silty / more clayey ? This is unclear... This is not coffee And the collaboration with the structural engineer is a bit hard as he still didn't really look into what we want to do. Despite all of our discussions, he keeps having in mind that we're using the same type of material that people usually use here, which are hand pressed bricks with 20% cement as a stabilizer... Nope, not the same...

week 19 - leap forward

Week 20 starting tomorrow !  We now have regular site meetings every Monday with the client and the main contractor, and the works have been steadily progressing since August.  We're starting racing a bit so that we really have the roofs in place before the rains come - but for now no sign of it, uuuf ! The Dorm was the occasion for the bricklayers to try a new way of laying stones... with less mortar than what they're used to. And they're managing pretty well !    very few men on this picture... the first Monday after pay day is always a bit difficult... I didn't realize the ground and ring reinforced concrete beams were going to take so much time to cure when the structural engineer n°1 proposed that... it's a bit unnerving to have to count 21 days before being able to do anything... especially since all these curves* make the shuttering all the more complicated ! (*inherited design from design architect) oh and soon we'll have comp...

Week ...? - 17/01 Preserving the trees

When you want to preserve the trees of the site you're building on, you have to go with some golden rules...  One of these is "you do not build too close from the trees", or else you'll damage the roots, and the tree you wanted to keep will die shortly... So the challenge was to build our stone boundary wall without damaging the roots of the beautiful Tree-on-the-Rock that is standing just at the limit of the site. And we did it ! It's such a nice place and will be perfect to come to meditate about the resilience of beings around us...